Excel Gantt chart template with progress tracking
The short version: This free Excel Gantt chart template draws a weekly timeline from your task dates and shades the finished part of each bar from a % done column. No macros, no add-ins. Change the dates and the chart redraws.

A Gantt chart is a bar chart of a schedule: tasks down the side, time across the top. Most people only need a simple one. This template is built from plain formulas and conditional formatting, so it works in any recent Excel. The tasks and dates in the sample are made up.

How the template works

The Gantt sheet has one row per task with Start, Days, End and % done. End is =B6+C6-1. Ten weekly columns sit to the right, with week-start dates calculated from the project start in B2. Each cell checks whether the task overlaps that week: =IF(AND($B6<=F$5+6,$D6>=F$5),IF(F$5+3<=$B6+$C6*$E6,"#","-"),""). A "#" is the done part of the bar and a "-" is the remaining part. Conditional formatting turns "#" green and "-" blue, so you see a bar instead of symbols.

Excel Gantt chart template with weekly columns and progress
Task table on the left, weekly bars on the right. Green is done, blue is remaining.

How to use it

1. Download the xlsx and open it in Excel. 2. Set the project start date in B2. 3. Replace the sample tasks and type each Start date and number of Days. 4. Update % done as work moves. 5. To add tasks, copy the last row down and extend the conditional formatting range (Home > Conditional Formatting > Manage Rules).

Limits to know about

This is a simple Gantt chart. It does not draw dependency arrows, and each column is one week, so tasks shorter than a week show as a single cell. If your project has many linked tasks and several people, a project tool will serve you better. For lighter work, a spreadsheet is faster to set up and easier to share.

Related

Prefer Google Sheets? Try the project management template for Google Sheets. More files are in our list of Excel templates for small business. If you have outgrown spreadsheets, see ClickUp vs Monday.com.

How to use the Excel Gantt chart template
The How to use sheet is built into the file.
Free download: Excel Gantt chart template with progress tracking (xlsx)
Download the free template

The bottom line

Keep the plan small, update % done once a week, and the chart stays honest.