How to Create a Gantt Chart in Excel: Step by Step (With Progress)

How to create a Gantt chart in Excel: stacked bar, no fill and reverse order
Illustration: How to create a Gantt chart in Excel

A Gantt chart shows a project as bars on a timeline, so you can see what starts when, how long each task takes and what overlaps. You can build one in Excel without extra software. This guide shows how to create a Gantt chart in Excel step by step with start dates and durations, then how to show progress and how to make the chart update when dates change. The tasks and dates are made up.

Excel Gantt chart data table: task, start date, duration and end date formula
A small table with made-up tasks (illustration).

Set up the data for an Excel Gantt chart

Excel has no built-in Gantt chart type, so we use a stacked bar chart and hide the first part of each bar. Start with a small table. Put these headings in row 1 and enter four example tasks below:

  • Task (the name)
  • Start date (a real date, such as 1 Dec 2026)
  • Duration (days) (a number)
  • End date (a formula)

In the End date cell, add the start date and the duration, then take off one day so a one day task starts and ends on the same day:

=B2+C2-1

Drag the formula down. Format the Start date and End date columns as dates. Keep the dates as real dates, not text, or the chart will not read them.

How to create a Gantt chart in Excel in 5 steps with a stacked bar chart
The five steps (illustration; menu names may differ slightly).

How to create a Gantt chart in Excel: step by step

  1. Select the Task, Start date and Duration columns. Do not select End date.
  2. Open the Insert tab, click the bar chart button and choose Stacked Bar.
  3. Click the blue bars, which are the Start date series, open Format Data Series and set the fill to No fill. Now only the Duration bars show.
  4. Click the task names on the left axis, open Format Axis and tick Categories in reverse order, so the first task is at the top.
  5. Remove the legend and add a clear chart title.

The chart now looks like a Gantt chart. Menu names can differ a little between Excel versions, but the idea is the same.

Tidy the date axis

The date axis may start far earlier than your first task. Click the date axis, open Format Axis and type the first start date into the Minimum box. Excel stores dates as numbers, so you may need to enter that number. To find it, copy your first start date into an empty cell and change its format to Number. Use the same method for the Maximum box if you want to cut the axis at the project end.

Excel Gantt chart with progress: days done and days left helper columns
Helper columns for a progress bar (illustration).

Excel Gantt chart with progress

To show progress, add a Percent complete column, then split each bar in two parts: the days done and the days left. Add two helper columns:

  • Days done: =C2*D2 where C2 is the duration and D2 is the percent complete
  • Days left: =C2-E2 where E2 is Days done

Build the chart from Task, Start date, Days done and Days left. Keep the Start date series with no fill, and give Days done a dark color and Days left a light color. The darker part of each bar then shows how much of the task is finished. Update the percent column as work moves on, and the bars change with it.

Excel Gantt chart with conditional formatting custom formula for start and end dates
The in-cell method (illustration).

A second method: Gantt chart with conditional formatting

You can also draw the bars in the cells. Put the dates of the project across row 1, starting in column E. Then select the grid under the dates, open Conditional formatting, choose a custom formula and enter:

=AND(E$1>=$B2,E$1<=$D2)

Here B2 is the start date and D2 is the end date. Choose a fill color. Every cell between the start and end of a task is colored. This method is easy to read on a screen, and it updates when you change a date. Our guide to conditional formatting explains custom formula rules in more detail.

How to make the Excel Gantt chart update automatically

The chart reads the cells, so it changes when you change a start date or a duration. To make new tasks appear, turn the data into an Excel table first: click a cell in the data and press Ctrl+T. A chart that uses a table grows when you add rows. If you work with a team, pair the chart with a task tracker and send a project status report each week.

Excel Gantt chart: common questions

Does Excel have a Gantt chart template?

Excel offers some project templates when you start a new file, but what is available depends on your version. The steps above work in any recent version without a template.

Can I add dependencies to an Excel Gantt chart?

Excel charts do not draw dependency arrows by themselves. A simple approach is to make a task start the day after another ends, with a formula such as =D2+1 in the next task's start cell. Then if the first task moves, the next one moves too.

Can I make a Gantt chart in Google Sheets?

Yes. The conditional formatting method works in Google Sheets in much the same way. See our Google Sheets dashboard guide for charts in Sheets.